Hartsfield-Jackson Atlanta International Airport said it terminated the contract with the Terminal Design Team for the design of the new International Terminal, citing the failure of TDT "to live up to its contractual obligations despite extended deadlines." In a statement, Airport GM Benjamin DeCosta said, "Among the major issues related to this action is the proposed terminal project design presented by the TDT that would have cost an estimated $140 million above the approved project ...

Subscribe to Access this Entire Article

"Other News - 08/15/2005" is part of ATW Plus, our online premium membership. Subscribing will provide you access to exclusive news, carefully researched airline financial, fleet and traffic data, plus the option to receive our popular, award-winning print magazine. To learn more, click here. If viewing via ATW Mobile, please login and click "Read web article" to view fully. Questions? ATWPlus@penton.com.